Setting out an extension: what happens on the day

What a setting out engineer does on site before your builder starts digging, what to have ready, how long it takes and what it costs. Written for homeowners and small builders about to start an extension.

The short answer

Setting out is where the extension on your drawings is marked on the ground before anyone digs. The engineer checks the drawings against the site, fixes a height to build from, pegs the corners and wall lines, checks they are square, marks the foundations and drainage, then walks your builder through it. With the drawings ready and the site clear, many single extensions take a half day on site, which with us costs £300 + VAT.

What setting out is, and why it matters for an extension

Your architect’s drawings say exactly where the extension goes and how big it is. Setting out turns those drawings into marks on the ground that your builder can dig and build to. On an extension it fixes six things:

  • Position: where the extension sits against the existing house.
  • Size: the length and width of the new walls, so the rooms come out at the size on the plans.
  • Square: corners at true right angles, so the walls, roof, doors and floor tiles all line up.
  • Levels: how deep the foundations go and how high the new floor sits against the existing one.
  • Boundary distances: the gap to the boundary shown on the approved drawings, which matters for planning and for your neighbours.
  • Drainage falls: new pipes with enough slope to carry water to the existing drains.

An extension is harder to set out than it looks, because it has to join a house that is rarely perfectly square or level. Our founder, Laurence Latham, is an MEng civil engineer with over 12 years of setting out on sites from house extensions to stadiums, and the same basics apply on every one. More on our house extension setting out service.

LL Engineering Group engineer setting out a residential building plot with two total stations
Setting out a residential building plot with two of our total stations. A single storey extension gets the same kit and the same checks.

What to have ready before the visit

Most hold ups on the day come from missing information. Before we arrive, have these ready:

  • Approved drawings with dimensions: the plans the extension was approved on, with the new walls dimensioned off the existing house. A PDF is fine, and a DWG is even better.
  • Building regulations drawings: these often carry more detail than the planning set, such as wall thicknesses and the drainage layout.
  • The structural engineer’s foundation details: the foundation type, width and depth, and any pads for steel posts.
  • A clear site: sheds, old slabs and rubble moved out of the footprint and the area around it, so the pegs can go in and stay put.
  • Access: a way into the garden for us and our equipment, and to the house wall the extension joins.
  • Your builder on site: the person who will dig to the marks should see them go in and agree the levels.
  • The existing wall and DPC: the damp proof course (DPC) needs to be visible, because the new floor level is usually worked out from it.
  • Where the drainage connects: the manhole the new drains will join, with the cover lifted if possible so its depth can be measured.

If your architect designed the extension from a topographical survey, send that too. Its levels are tied to Ordnance Datum, so we can set out to exactly the same heights. Not sure whether you needed one? Read do I need a topographical survey for planning.

What happens on the day, step by step

Every site is different, but a typical extension visit follows the same order.

1. Check the drawings against the site. Before any pegs go in, we measure the existing house and the boundaries and compare them with the drawings. Houses are not always exactly where the drawings show them, and finding that out now costs nothing. If something does not add up, we raise it so your architect can confirm what to do.

2. Fix a datum and a temporary benchmark. A datum is the height everything is measured from. On an extension it is usually taken from the existing house, such as the DPC or floor level, or from Ordnance Datum where the drawings use OS levels. We mark it as a temporary benchmark on something solid that will not move, so every trade works to the same height.

3. Set out the building lines and corners. Using a total station, we mark the corners and wall lines in the positions on the drawings, measured from the existing house and checked against the boundaries.

4. Put in offset pegs or profile boards. Corner pegs are lost as soon as the digger starts, so we also set offset pegs or profile boards back from the dig. Strings between them put the wall lines back whenever the builder needs them, from the trench to the first courses of brickwork. See profile boards vs total station for when boards alone are enough.

5. Check the diagonals and square. On a rectangle, the two diagonals are the same length when the corners are square. We check them, and the new walls against the existing house, before anything is marked for digging.

6. Mark the foundation widths. The trench edges are marked in paint to the width on the structural engineer’s or building regulations drawings.

7. Give levels for the dig and the slab. We give the builder the depth to dig to, the top of the foundation concrete and the level of the new floor slab, all from the datum.

8. Set out drainage runs and falls. New manholes, gullies and pipe runs are marked, with levels at each end so the pipes fall to the connection.

9. Record and hand over. We check the critical points before we leave, walk the builder through every peg and level, and give you a record of what was set out and the datum it was set from.

Not every extension sits on trench foundations. Our very first job, in 2017, was a restaurant extension in Southport built on pile caps and ground beams. We marked every element out in paint on the broken out slab, then checked it again before the concrete went in.

Ground beams and pile caps for a restaurant extension in Southport marked out in blue and yellow paint on the broken out slab
Ground beams and pile caps marked out in paint, ready for digging, on our first job in 2017. Follow it from paint marks to steel frame in the Southport restaurant extension case study.

How long it takes

Many single house extensions fit in a half day on site, a morning or an afternoon, when the drawings are clear and the site is ready. A larger extension, an awkward site or a lot of new drainage can take a full day, and some jobs need a second visit, for example to check levels before the slab goes down. We confirm the time on site when we quote.

What your builder does next

  • Dig the foundations: the builder digs the trenches to the paint marks and down to the depth given from the datum, keeping clear of the offset pegs.
  • Building control inspection: building control, from your council or an approved inspector, needs notice before the trenches are covered and will usually want to see them open before any concrete goes in. Your builder normally arranges this.
  • Concrete: the foundation concrete is poured to the level we gave, ready for the walls to go up to DPC and the floor slab to follow.
  • Keep the pegs safe: the offset pegs and benchmark carry the setting out through the build, so protect them from diggers and skips.

Problems good setting out prevents

These are the mistakes that are cheap to avoid on day one and expensive to fix once the concrete is in.

  • Building over the boundary: even a few centimetres over the line can lead to a dispute with your neighbour and, at worst, rebuilding a wall.
  • Walls out of square: small errors at the corners grow as the walls go up, and show up later in the roof, the doors and the floor tiles.
  • The wrong floor level: a new floor set too high or too low against the existing house leaves a step where the old and new rooms meet, or levels that don’t work with the DPC.
  • Drainage without fall: a pipe laid too flat, or a connection that turns out too shallow, means slow drains, blockages and digging up a new floor to fix it.

Every one of these is caught by checking before digging. That is the point of an independent setting out visit, and it is the same approach we bring to all our setting out services, on sites of every size.

What setting out an extension costs

We charge setting out by the half day or the day, and our rates include an experienced engineer and a calibrated Leica total station.

  • Half day, £300 + VAT (£360 including VAT): a morning or an afternoon on site, which suits many single house extensions.
  • Full day, £400 to £600 + VAT (£480 to £720 including VAT): where a job sits in the range depends on availability, how complex the work is and the roles required.
Total station and GNSS rover set up to set out a new build plot
A total station and GNSS rover set up on a new build plot. The calibrated Leica total station comes with the engineer and is included in our rate.

We are based in Crosby, Liverpool, and work across the North West, with travel added for sites further away. Send us your drawings or just the postcode and we will confirm a fixed price in writing before anything is booked. See all our setting out and survey prices.

Common questions

How much does it cost to set out an extension?

With us, a half day on site is £300 + VAT (£360 including VAT), which suits many single house extensions. A full day is £400 to £600 + VAT, depending on availability, how complex the work is and the roles required. A calibrated Leica total station is included. See our setting out and survey prices.

Can my builder set out the extension instead?

Many builders set out small extensions with tapes and string lines, and on a simple, flat site that can work. An engineer with a total station adds a fixed datum, checked corners and levels, and a written record, which is worth having on a tight boundary, a sloping site or where new drainage has to connect.

When should I book the setting out?

Once the drawings are final and your builder has a start date. Book it for just before the dig, so the pegs are not knocked out by other work, and send us the drawings beforehand so any questions are sorted before the visit.

Do I need to be there on the day?

It helps if you can be there at the start to give access and answer questions about the boundaries. The most important person to have on site is your builder, who will dig to the marks and needs to understand the pegs and levels.

Do I need a topographical survey before setting out?

Not always. Many small extensions are set out from the drawings and the existing house. If the site slopes, the council asked for levels, or your architect designed from a survey, a topographical survey tied to Ordnance Datum gives everyone the same heights to work to. Read do I need a topographical survey for planning.

Will the pegs last for the whole build?

Pegs inside the dig are lost when the trenches go in, which is why we also set offset pegs or profile boards back from the dig. Ask your builder to protect them, and if they are knocked out we can come back and reset them on a return visit.