Profile boards vs total station setting out: which do you need?
How profile boards work, what a total station setting out adds, when boards on their own are enough, when they are not, and the mistakes that put walls in the wrong place. Written for builders, groundworkers, site managers and homeowners.
The short answer
Profile boards hold the lines and levels while you dig and build. A total station puts those lines in the right place to begin with, from the coordinates on the drawings, and checks them. On a simple, square extension on flat ground, well clear of the boundaries, an experienced builder can manage with tapes, strings and boards. With a tight boundary, a slope, off-square walls, shallow drainage or piles, most jobs use both: an engineer sets the corners, boards and levels, and the builder works from the boards. With us, a half day is £300 + VAT.
How profile boards work
A profile board is a horizontal length of timber fixed to two pegs. There is one beyond each end of every wall line, set far enough back that the digger, the spoil heap and the trench sides will not move it.
Nails or saw cuts in the top of the board mark the lines, typically the face of the wall and both edges of the trench. A string pulled tight between matching nails on opposite boards gives the line on the ground, and where two strings cross is a corner. To set out with profile boards:
1. Fix the first line. Usually the face of the existing house, or a building line from the drawings measured off something that will not move.
2. Peg the corners. Tape along the line and set each corner with a 3-4-5 triangle, or 6-8-10 on a bigger building.
3. Put up the boards. Fix them clear of the dig, run strings over the corner pegs and mark the boards where the strings sit.
4. Check the diagonals. On a rectangle they are equal when the corners are square. Adjust until they are, then fix the nails for good.
5. Mark the dig and the levels. Drop the trench lines to the ground with a level, spray paint them, then take the strings down for the digger. Depths are measured down from boards set to one height, or given from a temporary benchmark with a rotating laser.
The strings then go back up to check the trench, the concrete and the brickwork up to the damp proof course (DPC).
What a total station setting out gives you
A total station measures angles and distances to a prism, to within a few millimetres. It puts each point where the drawings say, not where a tape from the nearest wall says. A visit gives you:
- Coordinates from the drawings: corners, wall lines, pads and drainage set out from fixed control points, so the building sits right against the house and the boundaries.
- Offsets: pegs or profile boards at a known distance back from the dig, so the lines can be put back after digging.
- Levels from a datum: a temporary benchmark tied to the datum on the drawings, either Ordnance Datum or the existing floor or DPC, with levels for the dig, the concrete and the slab.
- Checks: every key point checked a second way before anyone digs.
- Records: what was set out, and the datum the levels came from.
It does not replace the boards. Corner pegs are lost with the first bucket, so the lines still need holding outside the trench. The difference is that the boards are in the right place, with levels from a checked point.
When profile boards on their own are fine
Plenty of good builders set out small jobs themselves, and on the right job that is sensible. Tapes, strings and boards are usually enough when:
- The shape is simple: a rectangle, or close to it.
- The ground is flat: so a tape reads true distances and the levels barely change.
- It is well clear of the boundaries: a few centimetres either way would not matter.
- The drawings are clear: new walls dimensioned off a straight, sound wall of the house.
- The drainage is easy: a short run with plenty of fall to a manhole of known depth.
- The builder has done it before: and checks the diagonals and dimensions before digging.
Even then, check twice. A tape that sags or follows a slope sets the point short, and an error at the first corner carries round the whole building.
When profile boards are not enough
Boards hold lines. They cannot tell you whether those lines are in the right place.
- Tight boundaries: where the drawings show a set gap to the boundary, or the wall sits on it. Fences and hedges are not always where the drawing shows the boundary.
- Curved or off-square walls: bays, splayed corners, curves and buildings at an angle to the house. Strings only give straight lines and a 3-4-5 only gives a right angle, so these are set out point by point from coordinates.
- Slopes: the tape has to be held level and stepped down, the foundations may need to step, and the levels change across the footprint.
- Drainage with little fall: on a long, shallow run a few millimetres per metre matters, so the pipe levels need a checked datum, not a guess at the depth of the manhole.
- Piles: a piling rig leaves nowhere for boards to stand. Each pile is set out from scheduled coordinates, and its as-built position recorded before the pile caps are dug.
- Large or multi-plot sites: buildings, roads and drains that must fit together need one site grid and one set of control points, not boards on each plot.
- Anything made to the drawings: a steel frame, holding-down bolts, precast units or a timber frame kit arrives built to the drawings, so the foundations have to be too.
Most jobs use both
On most extensions and small builds, the answer is both. The usual approach is:
- The engineer sets the corners: from the drawings with a total station, checked against the house and the boundaries.
- Then the offsets: offset pegs or profile boards back from the dig, with each line marked and labelled.
- Then the levels: a temporary benchmark on something solid, and the levels for the dig, the concrete and the slab.
- The builder works from the boards: strings for the dig, the concrete and the brickwork, with a rotating laser for the levels.
- A return visit if needed: for example to check the drainage or the slab level before it is covered up.
The part that is expensive to get wrong, putting the building in the right place, is done once with the right kit, and the builder still has lines to work to every day. Our guide to setting out an extension walks through that visit step by step, and our house extension setting out page covers what is included.
Common profile board mistakes
Most setting out errors on small jobs come from these, not from the kit.
- Boards knocked: a digger, a dumper or a pallet of blocks moves a board and nobody notices. Keep plant away, check the diagonals again before each stage, and reset a moved board from the others, never by eye.
- Measuring from the wrong line: the string ends up on the trench nail when it should be on the nail for the face of the wall. Write on every board what each nail marks.
- Face of wall or centre line: drawings may dimension to the face of the brickwork, the face of the blockwork or the centre line. Mix them up and the wall moves by half its thickness or more. Agree what the boards show before anyone digs.
- Not checking the diagonals: a corner can look square and still be well out. On a rectangle, equal diagonals mean square corners.
- Levels from an unchecked point: a manhole cover, a kerb or the neighbour’s wall is not a datum. Take every level from one checked temporary benchmark.
How we work
We are based in Crosby, Liverpool, and since 2017 have worked on over 100 projects for more than 50 contractors. Our founder, Laurence Latham, is an MEng civil engineer with over 12 years of setting out, backed by an office team with 25 years’ combined site experience.
- Day rates: £300 + VAT a half day, or £400 to £600 + VAT a full day depending on availability, complexity and the roles required, with a calibrated Leica total station included. Travel for sites further from Crosby is shown in the quote, and longer bookings get a reduced day rate.
- Our own kit: Leica TS16 robotic total stations, Leica GPS and rotating lasers.
- Boards or offset pegs: we set offset pegs or profile boards back from the dig, and walk your builder round every mark before we leave.
- Doing it yourself: we hire out the same kit from one week, and run a 2-day setting out course for groundworkers and foremen who set out their own lines and levels.
See our setting out services and our setting out and survey prices.
Common questions
What are profile boards used for in setting out?
Profile boards hold the wall lines and levels outside the dig. Each board is fixed to two pegs beyond the end of a wall, with nails marking the face of the wall and the edges of the trench. Strings pulled between opposite boards put the lines back whenever they are needed, from digging the trench to laying the first courses of brickwork.
How far from the trench should profile boards go?
Far enough that the digger, the spoil heap and the trench sides will not move them. On most house foundations that means at least a metre beyond the edge of the trench, and more where a bigger machine is digging or the ground is soft. Keep them clear of the route the plant and deliveries will take, too.
How do you check profile boards are square?
Measure the two diagonals between the corners where the strings cross. On a rectangle, the corners are square when the diagonals are the same length. To set a right angle in the first place, use a 3-4-5 triangle, or 6-8-10 for a larger building. On any other shape, compare the diagonals with the lengths worked out from the drawing.
Do I need a setting out engineer, or can my builder use profile boards?
For a simple, square extension on flat ground, well clear of the boundaries, an experienced builder can set out with tapes and profile boards. Bring in an engineer for a tight boundary, a slope, off-square or curved walls, drainage with little fall, piles or a larger site. Many jobs use both: an engineer sets the corners, boards and levels, and the builder works from the boards. See our house extension setting out service.
Do you still need profile boards if a total station is used?
Usually, yes. Corner pegs set inside the dig are lost as soon as digging starts, so the lines have to be held outside the trench on offset pegs or profile boards. The engineer can set those as well, so the builder has lines to work from every day without needing the instrument back on site.
How much does total station setting out cost?
With us, a half day is £300 + VAT and a full day is £400 to £600 + VAT, depending on availability, complexity and the roles required, with a calibrated Leica total station included. Travel for sites further from our base in Crosby is shown in the quote, and longer bookings get a reduced day rate. See our setting out and survey prices.
Need the corners and boards set out?
Send us your drawings or a few details and we’ll come back with a clear quote, usually the same day.