What is a temporary benchmark (TBM)? Site levels explained

What a TBM is and why every site needs one, how Ordnance Datum differs from a site datum, how levels are carried around site, and the level terms on your drawings in plain English.

What does TBM stand for in surveying?

TBM stands for temporary benchmark, also written temporary bench mark. In surveying and construction, a temporary benchmark is a fixed point on site with a known height that every level on the job is measured from. It is usually a pin set in concrete, with its height in metres above Ordnance Datum (m AOD), the same zero as the drawings and the survey. A good site has two or three, clear of plant and checked against each other. Get the TBM wrong and everything set from it is wrong too.

What is a temporary benchmark?

Every height on a drawing, from the bottom of a trench to the finished floor, is a level: a height above a fixed zero, called the datum. To build to those levels, the site needs a physical point with a known height that everyone measures from. That is the temporary benchmark, usually a steel pin or nail set in concrete, or a mark on a solid kerb, labelled with its height. It is temporary because it only has to last for the job.

Every trade needs heights: formation for the groundworkers, the damp proof course for the bricklayers and falls for the drainage. With one agreed TBM, they all work to the same height. Without one, each picks its own, such as the existing floor or a manhole cover, and the levels drift apart. On bigger jobs the TBMs are part of the site control, alongside the stations that fix positions.

Ordnance Datum vs site datum

Ordnance Datum. The national height system for mainland Great Britain is Ordnance Datum Newlyn, based on mean sea level at Newlyn in Cornwall. A level of 12.350 m AOD means 12.350 metres above that zero, which is why levels on many drawings end in “m AOD”. Sewer records, flood levels and the survey can then all be compared directly. A topographical survey and the setting out that follows it should use the same datum. Our guide to what AOD means explains where the Newlyn zero came from and how it was levelled across the country.

Assumed site datum. A fixed point is simply given a height, often 100.000 m, so no level goes below zero. It suits a single building that does not tie in with levels outside the site. On an extension the datum is often taken from the existing house, such as the damp proof course, as our guide to setting out an extension describes. But its levels cannot be compared with sewer records or the site next door, and if the TBM is lost unrecorded, the datum goes with it.

The rule is simple: work to the datum the drawings use, and if they do not say which, ask before anything is built.

What happened to Ordnance Survey benchmarks?

The arrow pointing up to a horizontal bar, cut into old walls, churches and bridges, is an Ordnance Survey benchmark. Ordnance Survey no longer updates them. Apart from about 190 high-accuracy fundamental benchmarks, the network is no longer maintained, and OS warns that in old mining areas, where the ground has subsided, the benchmarks cannot be relied on. Elsewhere, buildings settle and walls are rebuilt, so a published height may no longer match the mark.

Today, heights on Ordnance Datum come from satellite positioning. OS Net, Ordnance Survey’s network of GNSS base stations across Great Britain, supplies the correction data behind the services survey grade GPS uses, and an OS model converts the satellite height to Ordnance Datum. GPS heights are good to a few centimetres, not millimetres, so the GPS fixes the datum and the TBMs carry it. Treat an old cut benchmark as a rough check at most.

Leica total station on a yellow tripod and a GNSS receiver with its controller on a red tripod, set up on a cleared development site
A Leica total station and GNSS receiver on site. The GPS ties the site to Ordnance Datum, and the total station carries the height more precisely.

What makes a good TBM

  • Stable: a pin in concrete, a solid kerb or a substantial wall. Never a fence post, a manhole cover or a peg in soft ground.
  • Out of the way and protected: clear of plant routes, the dig, spoil and scaffold, and fenced or boxed in so a dumper cannot clip it.
  • Marked and recorded: painted, labelled with its name and level, such as TBM1 12.350, and shown on a sketch with the datum, so nobody mistakes it for a setting out peg.
  • More than one: two, or three on most sites, spread around so each can be checked against the others. If one is knocked, the others show it.

How a TBM is set up

From GPS on Ordnance Survey heights. Where there is no survey control, survey grade GPS fixes two or more points in m AOD. The height difference between them is checked with a level or total station before the TBMs are set from them.

From the survey control. If the site has a topographical survey, its control stations and levels should be listed on the drawing. The engineer checks onto at least two and sets the TBMs from them, so the build sits on the same datum as the design.

Either way, each TBM is checked by a second route before anyone works to it.

3D ground model of a sloping site built from a topographical survey, coloured by level from 58.3 m to 67.2 m
A 3D ground model from one of our surveys, coloured by level from 58.3 m to 67.2 m above Ordnance Datum. Setting out from the same control keeps the build on those levels.

How to transfer a level around site

The most common tool is a level and staff, and the sums are simple.

  • Backsight: read the staff on the TBM and add it to the TBM level to get the height of the instrument. A TBM at 12.350 m and a reading of 1.420 m gives 13.770 m.
  • Foresight: read the staff on the new point and take it off the instrument height. A reading of 2.105 m puts the point at 11.665 m. Over longer distances, the level moves in stages, called change points.
  • Close the loop: finish back on the TBM, or on a second one. The difference from its known level is the misclosure, and on a site level run it should be a few millimetres at most. If it is more, find the mistake before anyone builds to it.

A robotic total station does the same job from angles and distances, across a large site or up a frame, and the rule is the same: start on a known point and finish on another. A rotating laser set from the TBM gives the groundworkers a level or a fall to dig to, so check it against the TBM each morning and whenever the tripod is knocked.

LLEG Leica robotic total station and kit case inside a large steel frame warehouse under construction
Our Leica robotic total station inside a steel frame warehouse. On a building this size, every level run closes back onto a known point.

Need a total station for your levels? We hire the same Leica TS16 robotic total stations our engineers use, with a current calibration certificate, from one week and delivered free on local North West hires. Or have our setting out engineers set and check the TBMs for you.

Level terms on drawings, explained simply

  • Reduced level (RL): any height worked out relative to the datum, rather than a raw staff reading. Spot levels on a survey are reduced levels.
  • Finished floor level (FFL): the top of the finished floor, often the key level on the job. Thresholds, steps and outside levels are set from it.
  • Formation level: the level the ground is dug to and prepared, ready for the sub-base or foundation concrete.
  • Top of concrete (TOC): the top of the foundation or slab concrete, given before the pour.
  • Invert level (IL): the lowest point inside a pipe, where the water runs. Drains are laid between inverts, and cover level minus invert level gives the depth to the invert.
  • Falls: often written as a ratio, such as 1 in 80, a drop of 1 m for every 80 m of pipe.

Common problems with TBMs and site levels

  • A TBM knocked, or on something that moves: a peg clipped by a dumper or a kerb lifted for a crossing. The levels change and nobody notices, unless there are other TBMs to check against.
  • Two datums on one job: one trade on an assumed 100.000 m, another in m AOD. Agree one datum and write it on the drawings and the TBMs.
  • Survey and design on different datums: a survey on an assumed datum and a drainage design in m AOD will not tie up. Check the datum on every drawing before setting out.
  • Levels from an unchecked point: a manhole cover, an old cut benchmark or a level someone remembered. Check it onto a second known level first.

How we work

We are based in Crosby, Liverpool, and every setting out visit starts with the control: we check the datum on the drawings and set or check the temporary benchmarks, tied to your survey or OS data.

  • Day rates: £300 + VAT a half day, or £400 to £600 + VAT a full day depending on availability, complexity and the roles required, with a calibrated Leica total station included. Travel is shown in your quote, and longer bookings get a reduced day rate.
  • Our own kit: Leica TS16 robotic total stations, Leica GPS and rotating lasers, all available to hire from one week.
  • Experience: our founder, Laurence Latham, is an MEng civil engineer with over 12 years of setting out. Since 2017 we have worked on over 100 projects for more than 50 contractors.

See our setting out services and prices. Our 2-day setting out course covers site control, temporary benchmarks and resections, at £350 + VAT per person for groups of 4 to 8, or £600 + VAT for a 1-to-1 day.

Common questions

What does TBM stand for in construction?

TBM stands for temporary benchmark: a fixed point on site with a known height, such as a pin set in concrete or a mark on a solid kerb, that every level on the job is measured from. It is called temporary because it only has to last for the build.

What is the difference between Ordnance Datum and a site datum?

Ordnance Datum Newlyn is the national zero for heights on mainland Great Britain, based on mean sea level at Newlyn in Cornwall, and levels on it are written as m AOD. A site datum is an assumed height, often 100.000 m, given to a fixed point on one site. It works for a single building, but its levels cannot be compared with sewer records, flood levels or surveys of neighbouring land.

Can I still use an Ordnance Survey benchmark?

Ordnance Survey no longer updates the old cut benchmarks, and warns that in old mining areas, where the ground has subsided, they cannot be relied on. Elsewhere, walls settle or are rebuilt, so a published height may no longer match the mark. One can be a useful rough check, but heights in m AOD now come from survey grade GPS, and are then carried around site with a level or total station.

How many TBMs does a site need?

At least two, and three on most sites, spread around so they can be checked against each other. Even on a small extension a second point is worth having, so that if one is knocked or moved it is spotted straight away rather than after the concrete is in.

How do you transfer a level from a TBM?

Set up a level and read the staff on the TBM. Adding that backsight reading to the TBM level gives the height of the instrument. Then read the staff on the new point and take that foresight reading off the instrument height to get its level. Finish the run back on the TBM or another known point, and check the misclosure is only a few millimetres before anything is built.

How much does it cost to have a TBM set up?

Setting or checking temporary benchmarks is part of our setting out visits. A half day, which suits smaller jobs such as a set of level checks, is £300 + VAT, and a full day is £400 to £600 + VAT, depending on availability, complexity and the roles required, with a calibrated Leica total station included. See our setting out and survey prices.

Sources

Checked October 2026.

Need levels you can trust on your job?

Send us your drawings, dates and site address, and we’ll confirm availability and a price in writing, usually the same day.