The short answer

A setting out engineer turns the drawings into marks on the ground, so everything is built in the right place and at the right height. That means checking the site control, taking coordinates from the drawings, setting out gridlines, piles, foundations, drainage and kerbs, giving levels to the trades, checking the work and recording what was built. If your job has gridlines, piles, drainage falls or a tight boundary, it needs one. If you hire a setting out engineer from us, a half day is £300 + VAT and a full day £400 to £600 + VAT, with a calibrated Leica total station included.

What is setting out in construction?

Every construction drawing gives a position and a height for everything on it. Setting out moves that information onto the site as pegs, nails, paint marks and levels that the builders can dig and build to.

That needs a fixed framework to measure from, called the site control: stations with known coordinates, usually tied to the Ordnance Survey grid or a site grid, and temporary benchmarks with known heights. Every trade then works from the same points and the same levels.

It is not a one-off. Each stage, from the piles to the last kerb, needs its own marks, checked before the next trade covers them up. See our setting out services.

A typical day for a setting out engineer

No two days are the same, but on a commercial or groundworks site the day usually runs like this.

1. Plan the day. The engineer, the site manager and the foremen agree what the trades need next, such as a row of piles, a drainage run or a bolt check, so nobody waits for marks.

2. Check the control. Control stations get knocked by plant and buried by spoil, so the engineer checks onto known points and benchmarks first. If the control is out, everything set out from it is out too.

3. Take the coordinates off the drawings. The engineer checks each drawing is the latest revision and loads the coordinates from the CAD file onto the controller. Clashes often turn up here, such as an architect’s dimension that doesn’t match the structural drawing, and go back to the designers before anything is built.

4. Set out the works. Gridlines, piles, pads and trenches, bolts, manholes and drainage runs, road edges and kerbs, with offset pegs set back from the dig so the lines survive the digger.

5. Give levels. Formation levels, top of concrete, slab levels, drainage inverts and kerb falls, plus a rotating laser so the groundworkers can dig and lay to level.

6. Check the work. Every point gets a second, independent check against the tolerance in the specification, and again before a pour, because once the concrete is in, mistakes are expensive.

7. Survey the as-builts. The engineer measures where the piles, inverts, bolts, slabs and columns actually ended up, and reports anything outside tolerance the same day.

8. Write up the day. What was set out, from which control, what was checked and what the as-builts showed, ready for the contractor’s QA file.

Engineers setting out precast concrete columns being craned into place, with a total station in the foreground
Setting out precast columns as they are craned into place. Positions and bearing levels have to be ready before the crane arrives. More on commercial setting out.

The kit a setting out engineer uses

  • Robotic total station: the main tool, measuring to a prism to within a few millimetres. A robotic one follows the prism, so one engineer can set out alone. Ours are Leica TS16s.
  • GPS (GNSS): quick on open ground for roads, plots and earthworks, but it works to centimetres rather than millimetres and struggles beside tall buildings or under steel.
  • Levels and rotating lasers: to carry heights around the site, and to give the groundworkers a level or a fall to dig and lay to.
  • Controller: the handheld computer that runs the instrument and holds the points for the job.
  • CAD software: AutoCAD, to take coordinates off the drawings and draw up the as-builts, with our own add-in, LL Tools.
  • The basics: pegs, nails, spray paint, string lines and a tape. Most of what the trades see is still a peg with a mark on it.
Setting out points shown on a Leica controller on site
Setting out points loaded on a Leica controller. The engineer picks a point and the instrument guides them to it on the ground.

Running the kit yourself? We hire the Leica TS16 robotic total stations our own engineers use, with a CS20 controller, 360 prism and calibration certificate, from one week. Prefer an engineer with it? See site engineer hire.

Setting out engineer vs site engineer vs land surveyor

The titles overlap and are often used loosely, but the differences are real.

  • Setting out engineer: puts the design on the ground. The work is control, setting out, levels, checks and as-builts.
  • Site engineer: usually a broader role. As well as the setting out, a site engineer often handles quality checks, coordinating the trades, design queries and the QA file. On a small job one person does all of it. See our site engineering services.
  • Land surveyor: measures what is already there. A topographical survey records the ground, buildings and features as they are, so the designers have something accurate to design on.

The kit is much the same, but the direction is opposite. The surveyor tells the designer what is there. The setting out engineer tells the builder where to build.

Do you need a setting out engineer?

Most construction jobs do, at least for part of the time.

  • Main contractors: gridlines, piles, steel and precast, with checked setting out, QA records and as-builts for handover.
  • Groundworkers: drainage to falls, roads, kerbs and slab levels, with records the main contractor will accept.
  • Developers: housing plots, roads and sewers that have to sit where the approved drawings say.
  • Homeowners: an extension on a tight boundary, on a slope or with new drainage. See house extension setting out, or our guide to setting out an extension.

Not every job needs an engineer. An experienced builder can set out a simple rectangular extension on flat ground, clear of the boundaries, with tapes, string lines and a level, checking the corners by measuring the diagonals. It gets risky with a tight boundary, a slope, walls off square to the house, drainage with little fall, or several trades needing the same levels. Then a few hours of an engineer’s time is money well spent.

What makes a good setting out engineer

  • Accuracy: calibrated kit, sound control and knowing the tolerances on the job.
  • Independent checks: no point is trusted until it has been checked a second way, from another station or by tape between points.
  • Records: daily records and as-builts showing what was set out, from where, and what was built.
  • Communication: telling the trades whether a peg marks the face of the wall or an offset, and saying plainly when something is wrong.
  • Reading the drawings: finding the clash on paper, before it is built.
Leica total station set up inside a large steel frame warehouse, beside an LL Engineering Group instrument case
Our Leica total station inside a steel frame warehouse. Once a frame is up, we check each column for position, level and plumb against the National Structural Steelwork Specification.

How to become a setting out engineer, and what it pays

If you like being outdoors, are good with numbers and enjoy seeing something built where you marked it, setting out is a good career. Routes in include:

  • A degree in civil engineering or surveying, then a graduate site engineer role.
  • An HNC or HND in civil engineering or construction, often studied part time while working.
  • An apprenticeship in civil engineering or site engineering, mixing college and site work.
  • NVQs and short setting out courses for groundworkers and foremen stepping up.

Most sites want to see a CSCS card, which usually means passing the CITB Health, Safety and Environment test first. SSSTS, the site supervisor safety course, helps once you supervise others. Most adverts we see for experienced setting out engineers in the North West sit around £40,000 to £55,000 a year.

Our 2-day setting out course is £350 + VAT per person for groups of 4 to 8, or £600 + VAT for a 1-to-1 day, with all the kit supplied and an LL Engineering Group certificate of completion. It is our own certificate, not an accredited qualification. Already setting out and want more time on the kit? Register your interest on our recruitment page.

How we work

We are based in Crosby, Liverpool, and since 2017 have worked on over 100 projects for more than 50 contractors. Our founder, Laurence Latham, is an MEng civil engineer with over 12 years of setting out, backed by an office team with 25 years’ combined site experience.

  • Day rates: £300 + VAT a half day, or £400 to £600 + VAT a full day depending on availability, complexity and the roles required, with a calibrated Leica total station included.
  • The same engineers: back each time, so nobody needs briefing from scratch.
  • Our kit: our own Leica TS16 robotic total stations, Leica GPS and rotating lasers for setting out, plus a Leica RTC360 laser scanner we can have on site at short notice, and our drone for as-built and progress records.
  • Timesheets signed off on site: every day is logged on our timesheet system and signed off on site, so the invoice matches what was agreed.

See our setting out and survey prices, or read what a setting out engineer really costs if you are thinking of employing one.

Common questions

What is the difference between a site engineer and a setting out engineer?

A setting out engineer focuses on putting the design on the ground: site control, setting out, levels, checks and as-builts. A site engineer usually does all of that plus wider duties, such as quality checks, coordinating the trades and raising queries with the designers. On smaller jobs they are often the same person.

Is a setting out engineer the same as a land surveyor?

Not quite. A land surveyor measures what is already on site, for example in a topographical survey, so the designers have accurate information to design on. A setting out engineer works the other way, taking the finished design and marking it on the ground. The kit is much the same, and many people do both.

How accurate is setting out?

With a calibrated total station and good site control, setting out is usually accurate to a few millimetres. The tolerance that matters is the one in your specification, which is tighter for steelwork and precast than for drainage or earthworks. GPS works to centimetres, so it suits roads, plots and earthworks rather than structures.

How much does a setting out engineer cost?

With us, a half day is £300 + VAT and a full day is £400 to £600 + VAT, depending on availability, complexity and the roles required, with a calibrated Leica total station included. See our prices, or compare the cost of employing one in our guide to what a setting out engineer really costs.

What qualifications does a setting out engineer need?

There is no single required qualification. Many come in through a civil engineering or surveying degree, an HNC or HND, or an apprenticeship, and some step up from groundworks with short setting out courses or an NVQ. Most sites also want a CSCS card, and SSSTS is useful once you supervise others.

Can I become a setting out engineer without a degree?

Yes. Plenty of setting out engineers started through an HNC, an apprenticeship or as groundworkers and foremen, and built up their skills on site. A practical course is a good first step, such as our 2-day setting out course, and once you have some site experience you can register your interest on our recruitment page.

Need a setting out engineer on your job?

Send us your drawings, dates and site address, and we’ll confirm availability and a price in writing, usually the same day.